Google commits $17 billion to its first Wyoming data center, powered by 702 MW of fuel cells

Google will invest $17 billion in its first Wyoming data center near Cheyenne, powered by a 702 MW fuel cell plant with carbon capture, and pay for all its power.

By Emre A.Published

Image Google published with the announcement covered in this storyTech AI Latest
Image published by Google with the announcement. Image: Google

Google announced on 5 November 2026 a $17 billion investment in its first data center in Wyoming, in Laramie County near Cheyenne, with Tallgrass Energy, Black Hills Energy, AEP and Related Digital. Power is to come from a 702 MW fuel cell project with carbon capture and storage, and Google says it will pay for all the electricity the campus uses and any grid upgrades. The site will be air-cooled. The announcement came two days after US elections that put data center growth on the ballot.

Key facts

  • Announced: 5 November 2026 (Google)
  • Investment: $17 billion, Google's first data center in Wyoming, Laramie County near Cheyenne
  • Partners: Tallgrass Energy, Black Hills Energy, American Electric Power (AEP), Related Digital
  • Power: 702 MW fuel cell project with carbon capture; Bloom Energy fuel cells owned and operated by AEP
  • Costs: Google says it will pay for all electricity used and any grid upgrades; the site is air-cooled
  • Not stated by Google: total computing capacity and a completion date for the whole campus

What Google announced

Google announced on 5 November 2026 that it will build its first data center in Wyoming, calling the project a $17 billion investment in the state. The campus is in Laramie County, near the state capital Cheyenne, and is being developed with four partners: Tallgrass Energy, Black Hills Energy, American Electric Power (AEP) and Related Digital. Google describes the $17 billion as a long-term commitment rather than a single near-term payment, and it held a community meeting in downtown Cheyenne that it says drew more than 200 residents.

The power plan is the unusual part. According to Data Center Dynamics and Interesting Engineering, the campus will be supplied by a 702 MW fuel cell project with carbon capture and storage, under a power purchase agreement Google signed with AEP in October. Bloom Energy will supply solid oxide fuel cells, which AEP will own and operate. The fuel cells run on natural gas, and the captured carbon dioxide is to be stored at Tallgrass Energy's Eastern Wyoming Sequestration Hub. Google is also evaluating carbon capture for Tallgrass's combined cycle gas turbines. The 702 MW figure describes the power plant, not the computing capacity of the data center, which Google did not state.

Paying its own way on power and water

Google says it will pay for all of the electricity the campus uses and cover the cost of any grid upgrades needed to serve it, so that the project does not push costs onto other customers of the local utilities. The data center will be air-cooled, which uses much less water than evaporative cooling, a point that matters in a dry state. The company also expects the project to generate significant local property tax revenue for Laramie County and its schools, though the figures in coverage vary and are left out here, as are job estimates, which differ between reports.

The commitment on power costs follows the same line as OpenAI's pledge the same day to pay full power costs at its own data centers and to stop asking public officials to sign nondisclosure agreements. Our reading: who pays for the grid is now the central political question for AI data centers in the US, and the large builders are trying to answer it before regulators and voters do. Wyoming's outgoing governor Mark Gordon has set his own expectations in an executive order titled Data Centers the Wyoming Way, which lists non-binding principles for developers.

The site and its history

The project is not new to Cheyenne. Cowboy State Daily reported in July that Google was the owner behind the site, renamed Project Tembo after Crusoe paused its own development, which had been called Project Jade, at the request of its customer. Data Center Dynamics described a parcel of about 716 acres south of Cheyenne, served by about 2.7 GW of power resources including reserve margins, and Oil City News reported in September that Google had pitched the campus to Laramie County. Those earlier reports describe a phased build. Data Center Dynamics also reported that Black Hills Energy plans to build 564 MW of gas generation and run a private microgrid to serve the campus, separate from the fuel cell plant now announced. How the two power sources will be combined, and in what order the buildings come online, is not explained in Google's post. Google's announcement does not give a total capacity or a date for the whole campus, and those details are not stated in the announcement.

Cheyenne already hosts other large data center projects: Microsoft has operated there for years and broke ground on a further campus in 2025, and Related Digital, one of Google's partners, is building a campus in the area that Governor Gordon has praised. For more on how hyperscalers are securing power, see Google's earlier deal for nuclear uprates with Constellation.

Why the timing matters

The announcement came two days after the US midterm elections, in which a number of winning candidates for governor, attorney general and Congress had pledged to slow or halt data center construction, according to NBC News. On 5 November the Nasdaq fell more than 5% as investors weighed the risk of tighter rules on AI infrastructure, with chip makers among the hardest hit: AMD and Nvidia shares fell sharply, by amounts that vary between reports. Against that backdrop, a $17 billion commitment that comes with its own power supply and a promise to cover grid costs reads as an attempt to show that new campuses can be built without raising local bills. Wyoming, a state that has courted data centers and produces natural gas, is a lower-risk place to build. Whether the fuel cell and carbon capture plan delivers the emissions cuts its backers describe will depend on capture rates that have not been published. More on capacity and power deals is in the AI chips and data centers section.

What changed

BeforeGoogle had no data center in Wyoming; its role in the Cheyenne campus was known only through local filings
AfterGoogle publicly committed $17 billion to the Laramie County campus, powered by a 702 MW fuel cell project with carbon capture, and pledged to pay all its power and grid costs
Who it affectsLaramie County and Wyoming utility customers, Google Cloud capacity planning, US debate over data center power costs

Questions people ask

How much is Google investing in Wyoming?
Google says its first Wyoming data center, in Laramie County near Cheyenne, is a $17 billion investment, announced on 5 November 2026.
How will Google's Wyoming data center be powered?
By a 702 MW fuel cell project with carbon capture and storage, with fuel cells from Bloom Energy owned and operated by AEP. Captured carbon dioxide is to be stored at a Tallgrass Energy sequestration hub.
Will Google's Wyoming data center raise local power bills?
Google says it will pay for all of the electricity the campus uses and for any grid upgrades it needs. The campus will be air-cooled to save water.

Sources

  1. Google's data center investment in Wyoming (Google, 5 Nov 2026)
  2. Google announces $17bn data center campus in Cheyenne, Wyoming (Data Center Dynamics, 5 Nov 2026)
  3. Google's Wyoming data center plan pairs gas power with carbon capture (Interesting Engineering, 5 Nov 2026)
  4. Google to invest $17 billion in Wyoming data center for AI work (Bloomberg, 5 Nov 2026)
  5. Say hello to Google, the mystery owner behind Wyoming's largest data center project (Cowboy State Daily, 8 Jul 2026)
  6. Stocks plunge as election outcome and AI worries crush tech shares (NBC News, 5 Nov 2026)

Reference pages

Spotted an error? See the corrections policy and tell the editor. Facts in this story come from the sources listed above; vendor claims are attributed.

Comments

Loading comments.

No links, no insults; comments that break the rules are not published. 0/1000